What a method statement is for
The permit desk and the client reviewer are trying to answer one question: do these people know how they will do this job, here, without improvising? A method statement (sometimes called a safe work method statement in other regions) is the written sequence that answers that question.
It sits with the risk assessment and, on many Gulf sites, with a JSA. Each document has a different job:
| Document | What it does | What it is not |
|---|---|---|
| Risk assessment | Identifies significant hazards of the activity and the controls needed to bring risk to a tolerable level | A step-by-step “how we will do it” narrative |
| Method statement | Describes the actual method, sequence, plant, access, people and hold points | A generic risk register or a training lecture |
| Job safety analysis (JSA) | Breaks the same job into steps, hazards and step-level controls, usually briefed at the workface | A substitute for the full method or the permit |
Suppose a contractor submits a “confined space method statement” that lists “isolate, ventilate, enter” and attaches a company logo. The vessel is a horizontal separator with a side manway, a nitrogen purge history, and a nearby live hot-work job. If none of that appears in the method, the reviewer has no reason to believe the writer has seen the job.
Sections that belong in the document
Use this outline and cut anything that does not apply. Do not pad it with policy slogans.
- Title, reference number, revision, date, and the exact location or tag number.
- Scope and limits: what is included, and what is deliberately excluded (for example, “this method does not cover hot work inside the space”).
- References: drawings, isolation certificates, client procedures, and the related risk assessment.
- People and competence: supervisor, trades, permit receiver, gas tester, attendant, fire watch — named roles, not “as required.”
- Plant, tools and materials, including access equipment and communication.
- Step-by-step method, in the order of work, with hold points (isolation proved, gas test recorded, client inspection, and so on).
- Permits and interfaces: which permit types, neighbouring work, and SIMOPS if other crews can affect the job.
- Emergency arrangements: alarm, rescue, muster, and who stops adjacent work.
- Approvals: author, reviewer, and the client or area authority if the site requires it.
If the job is work at height, the method should connect to the existing work-at-height risk assessment and any rescue arrangement, rather than inventing a second, conflicting height assessment.
A short worked example (illustrative)
Task: replace a 2-inch drain valve on a depressured, isolated, tagged line at grade, in a process unit, during a planned outage. This is a teaching outline, not a site-approved document.
- Confirm the isolation certificate, lock and tag numbers, and zero-energy proof with the area authority before tools come out.
- Set a small exclusion area so the flange is not in a walkway, and keep a spill tray and absorbents ready.
- Break the joint on the far side first, standing out of the line of fire, and check for residual content.
- Swap the valve, use the specified gaskets and torque sequence, and do not use a cheater bar on undersized tools.
- Reinstate, punch the tightness test or service leak check required by the permit, tidy the area, and only then sign off the permit.
Notice what the outline does not do: it does not copy a vessel-entry method, and it does not pretend a JSA is unnecessary. The JSA would still walk the crew through line-of-fire, residual energy and hand injury at the workface. A line-of-fire toolbox talk can support the briefing; it does not replace the method.
Why reviewers send them back
- The location is “site as required” instead of a tag number or grid.
- The sequence does not match the drawings or the isolation plan.
- Roles are copied from a template and include a fire watch for a job with no ignition source, or omit a gas tester for a job that needs one.
- Emergency rescue is “call the supervisor” with no equipment or access route.
- The revision history shows a title change but the steps still describe last month’s activity.
Write in short numbered steps that a supervisor can brief in ten minutes. If a step cannot be done as written, stop and revise the method before the permit is issued, not after the first problem appears.
1. What is the main purpose of a method statement?
A method statement is the written sequence for a defined job on a defined site. Policy text and after-the-fact reports are different documents.
2. How does a method statement differ from a JSA?
Both support the same job, but they are not duplicates. The method explains how the work will be done; the JSA tests each step for hazards and controls.
3. A reviewer rejects a confined-space method that never mentions the vessel tag, the manway, or a nitrogen history. Why is that a fair rejection?
A method must describe the actual job. Generic “isolate, ventilate, enter” text that could apply to any vessel does not give a reviewer confidence.
4. The crew finds that the planned access will not work and wants to use a different machine. What should happen first?
If the method changes, the document and the authorisation change first. A talk sheet is not a revised method.
5. Which item belongs in a method statement?
Hold points make the sequence auditable. Legal annexes and slogans do not tell a crew how to do the job.
Frequently asked questions
What is a method statement?
It is a written description of how a defined task will be carried out, including the sequence, people, plant, access, permits and emergency arrangements. It should be specific to the location and the activity.
How do you write a method statement?
Name the job and location, set the scope, list roles and equipment, write the steps in order with hold points, state the permits and interfaces, describe emergency arrangements, and get the required approvals. Then brief the people who will do the work.
What is the difference between a method statement, a JSA and a risk assessment?
The risk assessment decides what significant risks exist and what controls are needed. The method statement explains how the work will actually be done. The JSA walks through each step at a more detailed, workface level. One document does not replace the others.
What should a method statement include?
Identity and revision, scope, references, people and competence, plant, numbered steps with hold points, permits and SIMOPS, emergency arrangements, and approvals.
Is a SWMS the same thing?
Safe Work Method Statement is a term used widely in Australia and in some companies elsewhere. The intent is similar: a documented safe method for a high-risk task. Follow the format your client specifies, rather than forcing a foreign form name onto a Saudi or Gulf permit system.