An excavation permit checklist should help a team confirm what is below the ground and what may affect the excavation from above or beside it. It is a coordination record for a defined work area. It does not replace the competent assessment of ground conditions, protective systems, access or underground services.
Before using the checklist
Define the excavation footprint, intended depth, method and work sequence. Bring available services information and site knowledge together and arrange the required verification. Under US construction requirements, underground installation locations must be addressed before excavation, and competent-person inspections are required. Apply the correct jurisdiction and engineering requirements; a permit is not a universal design for a trench.
Copy and adapt: Use this original checklist within your controlled site process. Add the applicable references and retain evidence for each decision.
Excavation Permit Checklist
| Review item | What to confirm or record |
|---|---|
| Location and limits | Mark the approved footprint and scope and link current drawings and setting-out information. |
| Underground services | Record service information, coordination with relevant owners and the approved identification and verification method. |
| Ground and protection | Confirm competent assessment and the appropriate protective-system design or selection for the work. |
| Nearby structures | Review foundations, roads, temporary works and loads that could affect stability. |
| Plant and spoil | Define positions, access, edge protection and controls for vehicles, equipment and excavated materials. |
| Access and boundaries | Check safe entry and exit, barriers, public protection and the planned escape arrangements. |
| Water and atmosphere | Assess water accumulation and any potential atmospheric hazard; establish controls and monitoring where needed. |
| Inspection and change | Name the competent inspector and define reinspection and suspension triggers under the applicable system. |
A worked example
Illustrative example: a services drawing shows a cable outside the planned trench, while a site marker suggests a crossing within it. The permit reviewer records the discrepancy and holds the affected excavation. The relevant people resolve and verify the service position through the approved process before the limits are released. Assuming the drawing is accurate would leave the conflict unresolved.
Follow-up and records
Before each release, check the actual work area against the permit conditions. Changes in location, depth, loading, weather or ground condition may require a new assessment. Keep the inspection record traceable. At hand-back, record the excavation condition, temporary protection and any remaining restrictions, including arrangements for an excavation left open.
Record the date, location or asset, findings, action owner, due or hold point and closure evidence. Use Yes / No / Not applicable only with a reason where needed. A blank or unexplained tick should not hide an unresolved concern.
Track outstanding actions in your daily safety officer report. Review recurring problems through your safety committee action log.
Common questions
Does a permit remove the need for inspection?
No. The permit and the competent-person inspection perform different functions and should be linked.
Can the team extend the trench outside the marked area?
Only after the changed scope has been assessed and authorised through the relevant site process.