419 Welcome to your Saudi Aramco Work Permit Receiver Exam Name Email 1. What are the basic precautions for cold work? Select all items that apply. Fire watch Gas test Standby man Special work precautions PPE & Barricade and warning signs None 2. What must the issuer do if a joint site inspection is not done? A sign a designated representative Required barricades and warning sign Write why not on the work permit Tell his foreman None 3. What information must the gas tester enter on the work permit? LTX-310 expiry date, name and badge number Gas test results, name and badge number Badge and certificate number Gas test results and normal level None 4. Who should point out all hazards and write on the work permit? The fire watch The issuer The standby man The receiver None 5. What considered cold work? Scaffold building and grinding Abrasive blasting and painting Brush painting and abrasive blasting Sand removal and scaffold building None 6. What is oxygen deficiency? Less than 23.5% oxygen Higher than normal amount of oxygen A lower than normal amount of oxygen Oxygen that above it’s flash point None 7. What hazard would you find when doing hot work? Ignition switch Ignition source Ignition point Auto ignition temperature None 8. What happens if work must continue past the time the original permit was to expire? Keep working, but tell the issuer. Work can continue until the job is completed. Stop work and come back the next day. Extend the permit or issue a new one. None 9. The safety of work site is a sole responsibility of an issuer? False True None 10. Any worker can be a sign as standby man? True False None 11. Who can decided that work is a low risk and that a work permit is not needed? The issuer The department manager The receiver The superintendent None 12. What should be a assigned when working near combustible materials? Fire watch Fire men Standby man Flag man None 13. Where could an issuer find out which permit to issue for a special job? On the front of any work permit Corporate loss prevention manual On the back of any work permit Facility operating instructions None 14. (1) The issuer must stop work if ————-? (2) A pipe fitter can not work on the same pieces of equipment using welder’s permit because. Joint site inspections are not needed for pipefitters. Each type of work involves different hazards. Welders are usually contractors. Gas tests are not needed for pipefitters. None 15. Why is the check list section important to issuer and receiver? It tells them all precautions to take. It controls the receiver’s break time. It makes sure important steps have been taken. It defines the duration and scope of work. None 16. What are the basic precautions for confined space entry, select all items that apply. Install air mover All of Above Install lighting A sign a standby man Isolate, clean, and purge equipment Take gas tests None 17. What training should a fire watch have? Operate control room Operate fire equipment Operate heavy equipment Operate radio equipment None 18. Who must sign a work permit to extend it? The new area foreman and the new issuer Superintendent’s countersignature is required The new issuer, receiver, and gas tester The new issuer and receiver None 19. Which of the following is NOT a restricted area? Dump site. Loading pier. Gasoline station. Tank farm. None 20. Who is a work permit receiver? A person nominated by his supervisor A maintenance or contract worker A person certified to receive permits A qualified Saudi Aramco employee None 21. The issuer must try to start –up equipment at the field switch after it has been isolated and before work starts to make sure: Locks and tags are installed There is no tag in the area It can not accidently start The receiver’s tag is installed None 22. if a work permit is not issued during an emergency, what must be done to do the work? Joint site inspection. Wear Scott air Pak. Superintendent must approve. All safety precautions must be taken. None 23. Who install locks and tags first? electrical engineer Power distribution Operations Sceco None 24. Work permit authorize ……….. Specific tools at general location Specific work at specific location General equipment at all work site General work at specific plant None 25. what do you call an area where work permits are required? Dangerous area. Controlled area. Sensitive area. Restricted area. None 26. What must the issuer write on the work permit? Name, organization code and badge number Badge number and certificate expiry date. Gas test results, name and badge number Name, badge number, and certificate expiry date None 27. Who should keep the work permit? The receiver The issuer The fire watch The standby man None 28. “use a fire blanket” or “hand dig only” are example of what? Hazards precautionary hazards Regular precaution Additional precaution None 29. What are the basic precautions for hot work permit? Select all items that apply? Fire protection equipment Blind, isolate, clean, and purge equipment All of the Above Cover sewer drains Fire watch Gas test None 30. Who must sign the work permit to close it? Designated representative Issuer and receiver Gas tester, issuer and receiver Competent person None 31. What responsibility do issuers and receivers share when signing a work permit? Responding to emergency events Getting countersignatures from superintendent Monitoring the operation of process Maintaining safety conditions at the site None 32. The use of a vehicle in an operating area requires, which work permit? Release Entry Hot Cold None 33. What must the receiver do if he stops work? Tell the senior crafts man Tell his immediate supervisor Tell the issuer Tell the designated representative None 34. Restricted areas include which locations? Welding shops pump stations, and assembly area Dining halls, housing units, and operating area Gas plants, tank farms, and assembly areas Pump stations, tank farms, and gas well None 35. what type of work does the work permit system authorize? All work done by maintenance or contractors Non- hazardous work where safety is important Specific construction, maintenance, or repair work All work constructed for Saudi Aramco None 36. The information’s entered in the “exact work location” box is important Because it controls? How long the receiver can work What equipment the receiver can use How many workers can be at the job site Where the receiver can work None 37. Why must equipment be de-energized and depressurized before work is started? Accidental start-up could happen Purge gas can be lost Locks and tags will deteriorate Gas tests are not accurate None 38. work permit can be issued for up to 30 days if_______________ The work site is far away The receiver can not close the work permit Only cold work will be done It is highly unlikely that conditions will change None 39. A release of hazardous liquids or gases permit is required when? Operators release hydrocarbons to the flare Pipefitters open a line or install blinds Crafts man builds a scaffold Operations drain equipment None 40. Who decides whether an area should be restricted or not? The issuer The department manager The receiver The superintendent None 41. The receiver must stop work if_____________. the designated representative must leave The work site becomes un safe. He can not find the issuer. The issuer leaves the job site None 42. Which work permit requires sewer to be covered within 75 feet? Cold Entry Release Hot None 43. We use work permits in hazardous areas to identify——– Alternated representative Hazards and precautions Expired permit The designated representative None 44. What is the acceptable level of LEL to allow hot work 5% to 50% 10 to 100 PPM 21% 23.5% 0.0 PPM None 45. What is the purpose of the work permit system? To insure that the hot work is not done in restricted area. To authorize specific construction or maintenance work. To document where receiver start work for time keeping. what do you call an area where work permits are required? None 46. who is responsible for safety at the work site after a permit has been extended? The person who countersigned the permit. The original issuer and receiver. The issuer and receiver who signed the extension. The one who originally did the joint site inspection. None 47. What considered cold work? Scaffold building and grinding Brush painting and abrasive blasting Sand removal and scaffold building Abrasive blasting and painting None 48. The receiver can leave the job site any time as long as he gets the Permeation from his supervisor. False True None 49. Where must the receiver keep work permit after it is issued? In the control room With senior crew member Display at the job site or in his possession Within the 75 meter of the work permit None 50. Who should ask for work permit before they start working? The issuer The standby man The fire watch The receiver None 51. Who is responsible for the safety on the work site? The receiver Both issuer and receiver Both fire watch and the standby man The issuer None 1 out of 6 Please fill in the comment box below. Share 0 FacebookTwitterPinterestLinkedinRedditWhatsappTelegramEmail previous post Work Permit Receiver next post Saudi Aramco Permit Receiver Latest Questions and Answers