295 Welcome to your Saudi Aramco & Sabic Work Permit Receiver Question Answers let's get start Name Email 1. What are the primary hazards for excavations and trenching? Slip, trips and fall Toxic gases Oxygen enriched/deficient Collapse and cave in None 2. How to renew a work permit? The issuer and receiver coming on shift sign for renewal The permit receiver sign for renewal The supervisor signed it The permit issuer sign for renewal None 3. What are ‘hold tags’ used for? To explain reasons for locking out equipment. To replace padlocks and lockout devices. To isolate electrical circuit breakers. For hot work. None 4. Scaffold should not be erected near the excavation; it should be at least _ times the depth of the trench. 2 times 1.2 times 1.5 times None of above None 5. In Saudi Aramco, the maximum safe angle of the slope for type C soil is? 54 (Type A) None of above 34 (Type C) 45 (Type B) None 6. In what situation must lock and tag be installed? All types of jobs. Before issuing work permit. When instructed by the issuer. When the energy can cause injury. None 7. How is hot work permit different from cold work permit? Hot work identify the permit issuer. Hot work identify potential source of ignition. Hot wok identify fuel source. Hot work is red. None 8. A work permit may be extended for one (1) additional operation shift, if: Only cold work is being done. All hot work has been completed. The new on-coming issuer and receiver agree on conditions and sign the permit to extend it. The work is almost complete. None 9. Any work that develops heat or provides an ignition source in a restricted area requires what type of work permit? Confined Space Entry. Cold Work. Hot Work. Release Permit. None 10. A _________should be used for the erection of scaffolding. Release of Hazardous Liquids or Gases Work permit Cold Work permit. Hot Work permit. Confined Space Entry Work permit. None 11. This _________system is mandatory when responding to H2S emergencies or working in hazardous areas; Buddy. Sewage. LOTO. GFCI. None 12. Orientation is part of the important aspects of Emergency Preparedness in Saudi Aramco that includes; Correct actions on hearing alarms Knowing the location of the mess hall/tea room Accessing the restricted offices Wearing your preferred dress None 13. What information the work permit issuer explain to the receiver before issuing EOLB permit? Hazard of permitting. Responsible persons Duration of work permit Hazards of the chemical None 14. Testing of H2S requires SCBA? False True None 15. A ____________is anything that can have an adverse impact on your safety. None of above Both health & safety Hazards Safety Hazard Health Hazard None 16. What are warning signs use for? Identify restricted areas Identify hazard. Decoration. Identify restricted activities. None 17. Hydrogen Sulfide (H2S) may react and explode when in contact with this Acid; Citric Acid Hydrochloric Acid Nitric Acid Muriatic Acid None 18. The confined Space Entry permit requires that: Non-sparking tools be used. Only hot work can be done. Only cold work can be performed. The confined space is properly isolated. None 19. Who may approve critical lift plans? Rigger II Rigger III Division Head Rigger I None 20. What are the basic safety measures to protect the driver from fall when driving near the excavation? Standby man/barricade. Barricade/signage. Barricade/blinker light. Signage/standby man None 21. Which of the following answers best describes a Work Permit Receiver? Any maintenance or construction supervisor. Craftsmen, or others, who have been certified to receive work permits. Only Saudi Aramco supervisors. All electrician, but not all welders. None 22. The scaffold inspector must sign the tags for all scaffolds above 6m? False True None 23. Wind direction must be considered when a permit is issued because: Flammable gases may be blown towards an ignition source. Because work must always take place downwind of the release. Dust particles may be blown into opened lines or vessels. Items may be blown to the site making the work area untidy. None 24. The receiver’s copy of the work permit which is currently in use should be: Kept at the Maintenance or Construction office. Posted or readily available at the job site. Posted in the control room. Kept with the Maintenance or Construction foreman. None 25. What is a safety hazard? Gravity. Electrical. All of above. Mechanical. None 26. When to stop and cancel a work permit? If the receiver leave the site. Is the hazard is not in the work permit. If the work has no signage. If the work has no barricade. None 27. Where are work permits required? All restricted areas. All assembly points. All fenced areas. All Saudi Aramco areas. None 28. When can an electrician use a welder’s work permit? Never If both the issuer and receiver agree and state so on the permit form. When the foreman gives his permission. When they work on the same equipment at different times. None 29. Restricted in Saudi Aramco are: Oil and gas plant/loading pier/office. Tank farm/plant pump station/warehouse. Air fueling operation/bulk plant/store room. Marine vessel/sewage treatment/plant/sump. None 30. The duration for renewal of work permit is __. Two shifts. Three shifts. One shift. No renewal of permit. None 31. What must be done when personnel working in the equipment could be injured by residual energy in the equipment? Isolate and apply lock and tag. Do not allow work. Issue work permit. Let him use PPE. None 32. In what order should hydrocarbon process equipment be prepared before welding the equipment? Gas test, isolate, drain content Isolate, drain, purge, gas test. Isolate the equipment. Clean, drain, gas test None 33. The purpose of hazard recognition is to __________hazards before they can cause an incident. Eliminate Identify Control Minimize None 34. Which of the following is not the example if unsafe act? Damaged/defective/incorrect equipment. Operating equipment without proper training or certification. Using defective equipment. Improper use of equipment. None 35. When working in noisy area what issuer will suggest. Goggle. Gloves. Earmuff. None 36. Eliminate and Isolation are? Administrative control All of above PPE Engineering control None 37. Toxic and flammable gases could be found in: Excavations. Elevators. Office buildings. Lakes or rivers. None 38. What is NORM? Neutrally Occurring Radioactive material. None of above. Naturally Occurring Radioactive material. Normally Occurring Radioactive material. None 39. A ______________is a work permit process that helps identify, control, eliminate or minimize any hazards before work can begin, and then ensure that the area is safe when the work is complete. Work Permit system Joint Site Inspection Hazard Analysis Checklist Job Safety Analysis (JSA) None 40. Common Hazard in Saudi Aramco are slip, trips and falls, that are caused by: Dry Floors and well-arranged cables Good Housekeeping Uneven Floor Surfaces and and Changes in Level. Floors with flat surfaces None 41. Filing of work permit Work permit should be kept in four months. Work permit should be kept in one month. Work permit should be kept in three months. Work permit should be kept in two months. None 42. Heavy equipment operations are the most common cause of work related fatalities in Saudi Aramco. True False None 43. Ladders should extend at least _ ft. above the landing area? 5 3 4 2 None 44. Respiratory protection equipment authorized to be used in Saudi Aramco are; SCBA/SABA SABA/SCBC STBA/SCBA. STBA/SABA. None 45. When must receiver stop the work? During inspection. Nobody can stop work. If stated in the duration box. During walkthrough. None 46. Who is jointly responsible for the safety of people and equipment at the work site? The issuer and receiver. Operations and maintenance engineer. The issuer, receiver, gas tester and Loss Prevention representative The receiver and other workers at the job site. None 47. Why must the work permit issuer check the crane operator certificate before he issue work permit To identify his company To make sure he own the equipment To check the equipment To prove he is competent None 48. If the receiver must leave the job site, the work permit can be left with: The receiver is not allowed to leave the job site under any circumstances. A senior crew member who understands the job and the conditions stated on the work permit. Anyone, as long as the permits remain on the job site. Anyone who can read the work permit. None 49. What should be the first step in controlling the hazards on the workplace? Eliminate Isolate Wear PPEs Reduce None 50. ho is the part of Joint Site inspection? Work Permit Receiver. Work Permit Issuer. Both. None of above. None 1 out of 10 Please fill in the comment box below. Share 0 FacebookTwitterPinterestLinkedinRedditWhatsappTelegramEmail previous post Saudi Aramco Safety Officer Evaluation Online Exam next post work permit receiver saudi aramco questions and answers